PMP Mock Test 8
Quiz-summary
0 of 200 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- 81
- 82
- 83
- 84
- 85
- 86
- 87
- 88
- 89
- 90
- 91
- 92
- 93
- 94
- 95
- 96
- 97
- 98
- 99
- 100
- 101
- 102
- 103
- 104
- 105
- 106
- 107
- 108
- 109
- 110
- 111
- 112
- 113
- 114
- 115
- 116
- 117
- 118
- 119
- 120
- 121
- 122
- 123
- 124
- 125
- 126
- 127
- 128
- 129
- 130
- 131
- 132
- 133
- 134
- 135
- 136
- 137
- 138
- 139
- 140
- 141
- 142
- 143
- 144
- 145
- 146
- 147
- 148
- 149
- 150
- 151
- 152
- 153
- 154
- 155
- 156
- 157
- 158
- 159
- 160
- 161
- 162
- 163
- 164
- 165
- 166
- 167
- 168
- 169
- 170
- 171
- 172
- 173
- 174
- 175
- 176
- 177
- 178
- 179
- 180
- 181
- 182
- 183
- 184
- 185
- 186
- 187
- 188
- 189
- 190
- 191
- 192
- 193
- 194
- 195
- 196
- 197
- 198
- 199
- 200
Information
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 200 questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 points, (0)
Categories
- Multichoice 0%
-
Now, the time for the revelation!
Congratulations, if you have scored more than 85%…… you have real grip on PMP. But we still recommend keep practicing
If you have scored less than 85%, you still need to work on it. Kindly revise the training session videos, mind map and book to gain a better score in PMP exam.
Pos. | Name | Entered on | Points | Result |
---|---|---|---|---|
Table is loading | ||||
No data available | ||||
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- 31
- 32
- 33
- 34
- 35
- 36
- 37
- 38
- 39
- 40
- 41
- 42
- 43
- 44
- 45
- 46
- 47
- 48
- 49
- 50
- 51
- 52
- 53
- 54
- 55
- 56
- 57
- 58
- 59
- 60
- 61
- 62
- 63
- 64
- 65
- 66
- 67
- 68
- 69
- 70
- 71
- 72
- 73
- 74
- 75
- 76
- 77
- 78
- 79
- 80
- 81
- 82
- 83
- 84
- 85
- 86
- 87
- 88
- 89
- 90
- 91
- 92
- 93
- 94
- 95
- 96
- 97
- 98
- 99
- 100
- 101
- 102
- 103
- 104
- 105
- 106
- 107
- 108
- 109
- 110
- 111
- 112
- 113
- 114
- 115
- 116
- 117
- 118
- 119
- 120
- 121
- 122
- 123
- 124
- 125
- 126
- 127
- 128
- 129
- 130
- 131
- 132
- 133
- 134
- 135
- 136
- 137
- 138
- 139
- 140
- 141
- 142
- 143
- 144
- 145
- 146
- 147
- 148
- 149
- 150
- 151
- 152
- 153
- 154
- 155
- 156
- 157
- 158
- 159
- 160
- 161
- 162
- 163
- 164
- 165
- 166
- 167
- 168
- 169
- 170
- 171
- 172
- 173
- 174
- 175
- 176
- 177
- 178
- 179
- 180
- 181
- 182
- 183
- 184
- 185
- 186
- 187
- 188
- 189
- 190
- 191
- 192
- 193
- 194
- 195
- 196
- 197
- 198
- 199
- 200
- Answered
- Review
-
Question 1 of 200
1. Question
During the project, you and your team discovered that a key project component was stolen. As this was not planned for, the team decided to launch the product without the stolen component. This is an example of?.
Correct
Work around. Since this was not planned for and the solution was arrived at during the project execution, this is referred to as work around. The other options are risk response strategies that are worked on during the planning process group.
Incorrect
Sorry, that was incorrect.
-
Question 2 of 200
2. Question
As part of Quantitative Risk Analysis, a project manager has derived four packages with the following probability and impact. Using EMV (Expected Monetary Value) which one should he use in the project?
Correct
Work package I : Probability 15% & Impact $ 20,000. EMV = Probability * Impact. If the impact is positive, then it is opportunity and if the impact is negative then it is threat. From the given options, all are opportunities and the one which is highest should be the right option.
Incorrect
Sorry, that was incorrect.
-
Question 3 of 200
3. Question
A project manager is involved in the procurement management process in a centralized contracting environment. He is assigned a full-time contract manager who reports to him for the project. Under this scenario, which activity would a project manager NOT be expected to carry out or complete?.
Correct
Provide increased expertise in contracting and also guide the team on standardized company practices. The project manager is working in an organization with a centralized contracting group. He has also been assigned an experienced full-time contract manager who would be a specialist in contracting procedure. In these circumstances, it is not expected for a project manager to provide guidance on organization contracting policies.
Incorrect
Sorry, that was incorrect.
-
Question 4 of 200
4. Question
A project manager knows that managing the expectations of stakeholders helps to increase the probability of project success by ensuring that stakeholders understand the project benefits and risks. For this process, he could use all of the following tools and techniques EXCEPT?
Correct
Issue log. An issue log is an input to the process manage stakeholder expectations. All others are tools and techniques for the process. For more information, please refer to PMBOK 5th edition Project Communication Management PN 404.)L2) Issue log. An issue log is an input to the process manage stakeholder expectations. All others are tools and techniques for the process. For more information, please refer to PMBOK 5th edition Project Communication Management PN 404.
Incorrect
Sorry, that was incorrect.
-
Question 5 of 200
5. Question
A cost-plus-incentive-fee (CPIF) contract has an estimated cost of $150K with a predetermined fee of $15K and a share ratio of buyer to seller equal to 70/30. The actual cost of the project is $120K. How much savings did the seller make in total and out of total savings how much did he make because of the incentive?
Correct
$30K, $9K. Correct Answer is ‘A’. The estimated cost of project is $150K, the actual cost of project is $120K. This implies a net savings of $30K. The sharing ratio is 30% for the seller which is = $9K. The total value of the amount received by seller is = $120K+$9K+15K = $144K (actual cost + incentive + fixed fee).
Incorrect
Sorry, that was incorrect.
-
Question 6 of 200
6. Question
Which is the best way of selecting a project, other things being constant?
Correct
The criteria for selection with regard to NPV and BCR should be that projects with higher values should be selected, hence options C and D are ruled out. Compared to payback period, IRR is a more reliable measure since it considers time value of money, so A is a better option than B.
Incorrect
Sorry, that was incorrect.
-
Question 7 of 200
7. Question
Which of the following is the correct formula for calculating the present value of a business or organization? Note: R = interest rate, n = time periods
Correct
This is the correct formula for calculating present value. Therefore the correct option is A.
Incorrect
Sorry, that was incorrect.
-
Question 8 of 200
8. Question
Which type of leadership style is most appropriate when managing large numbers of low skilled workers?
Correct
Autocratic. Correct Answer is ‘A’. Autocratic is the right type of leadership style for managing large numbers of low skilled workers.
Incorrect
Sorry, that was incorrect.
-
Question 9 of 200
9. Question
The project sponsor wants a 10% reduction in costs estimates prepared by the project team entrusted with the objective of improving the IT infrastructure downtime Service Level Agreement (SLA) by 3%. Which of the following would be the best course of action for the project manager?
Correct
Provide details of an accurate estimate with supporting documentation. Correct Answer is ‘A’. While options B and C appear likely to be exercised under the situation, a professional project manager would stand by accurate estimates and secure the approval of management.
Incorrect
Sorry, that was incorrect.
-
Question 10 of 200
10. Question
The major type of standard warranty that is used in the business environment is:
Correct
Correct Answer is ‘A’. The two types of warranties are express and implied. Express involves an actual promise specifically stated or expressed in a contract or an agreement. Implied means the terms of the warranty are created by the law regardless of the words of the parties in the contract or the agreement.
Incorrect
Sorry, that was incorrect.
-
Question 11 of 200
11. Question
As a project manager, you are asking each of your team members to give time estimates of their activities and calendar dates when they are available to work on those activities. What exactly are you doing?
Correct
Schedule Development. Schedule development is the process of assigning calendar dates of when each activity will be done and by whom. This is exactly what the project manager is doing. You can find out more about each of the project time management processes by referring to Lesson no. 6 of Simplilearn PMP Preparation Course.
Incorrect
Sorry, that was incorrect.
-
Question 12 of 200
12. Question
Which of the following documents has information regarding how people should be informed about the project’s progress?
Correct
Communication management plan explains about how the progress report, the frequency, technology to be used are mentioned.
Incorrect
Sorry, that was incorrect.
-
Question 13 of 200
13. Question
Which of the following is NOT a tool or technique of monitor and control risks?
Correct
Work performance information is an input to that process which means it needs to be gathered BEFORE you start monitoring and controlling your risks
Incorrect
Sorry, that was incorrect.
-
Question 14 of 200
14. Question
Which of the following is not a technique for determining project budget?
Correct
Analogous Estimating. Analogous estimating is a technique of cost estimation and not cost budgeting. The other three are techniques of cost budgeting. Be prepared for such straight forward questions on inputs, outputs and tools and techniques of project management processes.
Incorrect
Sorry, that was incorrect.
-
Question 15 of 200
15. Question
A project team is working on constantly reviewing and making sure that the right processes are being followed. Which process is being worked on?
Correct
Quality assurance focuses on the process and is done throughout the project execution
Incorrect
Sorry, that was incorrect.
-
Question 16 of 200
16. Question
You need to determine when to release resources from your project. Which part of the staffing management plan will be most useful for this?
Correct
Resource Histogram. A resource histogram is a bar chart that shows the amount of time that a resource is scheduled to work over a series of time periods.
Incorrect
Sorry, that was incorrect.
-
Question 17 of 200
17. Question
Which of the following is the MOST appropriate statement to describe a Project Management Office?
Correct
A PMO is supposed to be a center of excellence for project management in an organization
Incorrect
Sorry, that was incorrect.
-
Question 18 of 200
18. Question
Two project managers have just realized that they are in a weak matrix organization and the power as project managers is quite limited. One figures out that he is really a project expediter, and the other realizes he is really a project coordinator. How is a project expediter different from a project coordinator?
Correct
The project coordinator reports to a higher-level manager and has authority to make some decisions. The project expediter has no authority to make decisions.
Incorrect
Sorry, that was incorrect.
-
Question 19 of 200
19. Question
The previous project manager for your project managed it without much project organization. There is a lack of management control and no clearly defined project deliverables. Which of the following would be the best choice for getting your project better organized?
Correct
Developing lessons learned would help improve subsequent phases, but would do nothing for control or deliverables. Having plans for each work package would help control each phase, but would not control the integration of those phases into a cohesive whole. A description of the product of the project would help, but that would not improve both control and deliverables for each phase. Effective project management requires a life cycle approach to running the project. Adopting a life cycle approach is the only answer that covers both control and deliverables.
Incorrect
Sorry, that was incorrect.
-
Question 20 of 200
20. Question
In which project management process group is the detailed project budget created?
Correct
Notice the use of the word “detailed.” Such a budget is created during project planning.
Incorrect
Sorry, that was incorrect.
-
Question 21 of 200
21. Question
The best time to assign a project manager to a project during:
Correct
The project manager should be assigned during project initiating.
Incorrect
Sorry, that was incorrect.
-
Question 22 of 200
22. Question
Which of the following is an output of the collect requirement process?
Correct
The project scope statement is an output of the Define Scope process. The work breakdown structure is an output of the Create WBS process. Scope change requests are outputs of the Validate Scope and Control Scope processes. The requirements traceability matrix is an output of the Collect Requirements process, and is used to track the requirements throughout the life of the project.
Incorrect
Sorry, that was incorrect.
-
Question 23 of 200
23. Question
A project manager for a small construction company has a project that was budgeted for US $130,000 over a six-week period. According to her schedule, the project should have cost US $ 60,000 to date. However, it has cost US $ 90,000 to date. The project is also behind schedule, because the original estimates were not accurate. Who has the primary responsibility to solve this problem?
Correct
Did you get lost looking at all the numbers presented in this question? Notice that there are no calculations required, simply an understanding of what the problem is. This question describes schedule management, which is a responsibility of the project manager.
Incorrect
Sorry, that was incorrect.
-
Question 24 of 200
24. Question
Which type of cost is team training?
Correct
You are training the team on skills required for the project. The cost is directly related to the project and thus a direct cost.
Incorrect
Sorry, that was incorrect.
-
Question 25 of 200
25. Question
Early in the life of your project, you are having a discussion with the sponsor about what estimating techniques should be used. You want a form of expert judgment, but the sponsor argues for analogous estimating. It would be BEST to:
Correct
This is a tricky question. Determining why the sponsor wants such an accurate estimate sounds like a good idea at first. However, analogous estimates are less accurate than other forms of estimating, as they are prepared with a limited amount of detailed information. Reading every word of this choice helps eliminate it. In order to pick the best answer, you need to realize that analogous estimating is a form of expert judgment.
Incorrect
Sorry, that was incorrect.
-
Question 26 of 200
26. Question
Pareto diagram help the project manager:
Correct
Fishbone diagrams are often used to stimulate thinking and to explore a desired future outcome. Determining whether a process is out of control is a function of control charts. Only focusing on critical issues to improve quality relates to Pareto diagrams.
Incorrect
Sorry, that was incorrect.
-
Question 27 of 200
27. Question
What does a resource histogram show that a responsibility assignment matrix does not?
Correct
The responsibility assignment matrix maps specific resources to the work packages from the WBS. On a resource histogram, the use of resources is shown individually or by groups over time.
Incorrect
Sorry, that was incorrect.
-
Question 28 of 200
28. Question
A project manager is creating a risk response plan. However, every time a risk response is suggested, another risk is identified that is caused by the response. Which of the following is the best thing for the project manager to do?
Correct
Did you realize this question describes secondary risks? Identifying secondary risks is an important part of completing the Plan Risk Responses process. With that in mind, the best thing to do is to document the newly identified risks and continue the Plan Risk Responses process.
Incorrect
Sorry, that was incorrect.
-
Question 29 of 200
29. Question
Which of the following BEST describes the main purpose of the project charter?
Correct
It authorizes the project manager to work on the project.
Incorrect
Sorry, that was incorrect.
-
Question 30 of 200
30. Question
At the close of your project, you measure the customer satisfaction and find that some customer needs were not fully met. Your supervisor asks you what steps you took on your project to improve customer satisfaction. Which subsidiary plan would you consult to determine this information?
Correct
Quality management plan
Incorrect
Sorry, that was incorrect.
-
Question 31 of 200
31. Question
A junior project manager at your company does not know how to perform earned value analysis. You spend a weekend with him to teach him how to do this. This is an example of:
Correct
Contributing to the project management body of knowledge
Incorrect
Sorry, that was incorrect.
-
Question 32 of 200
32. Question
Your are managing a project to build a new wing onto a local school building over a summer break. One night, the school and your construction site are destroyed by a tornado. Your client demands that you continue work despite the disaster, but your consult the contract, and find a clause that states that you are not responsible for any more work. This is referred to as:
Correct
A force majeure clause
Incorrect
Sorry, that was incorrect.
-
Question 33 of 200
33. Question
You are in the process of estimating the number of work periods that will be needed to completeindividual schedule activities. All of the following are valuable inputs to this process except:-
Correct
Schedule model data
Incorrect
Sorry, that was incorrect.
-
Question 34 of 200
34. Question
For a large and complex project with cross-functional project needs, the followingorganizational structure gives considerable authority to project manager:
Correct
Functional Organization
Incorrect
Sorry, that was incorrect.
-
Question 35 of 200
35. Question
Consider the project Integration Management knowledge area. Which of the process are not included?
Correct
Report performance
Incorrect
Sorry, that was incorrect.
-
Question 36 of 200
36. Question
Which of the following are false regarding corrective actions?
Correct
. Corrective actions generally do not require root cause analysis to identify the cause of variation
Incorrect
Sorry, that was incorrect.
-
Question 37 of 200
37. Question
The following is an example of a constraint associated with project scope that limits the team’s option in scope definition:
Correct
A Pre-Defined Budget
Incorrect
Sorry, that was incorrect.
-
Question 38 of 200
38. Question
Inputs to Develop Project Team include all except:
Correct
Team Performance Assessment
Incorrect
Sorry, that was incorrect.
-
Question 39 of 200
39. Question
You have taken information on project scope and resources and then developed durations for input to schedules. Since there was very limited information about the project, you used actual duration of a previous, similar activity as the basis for estimating future activity. This type of estimating can also be referred to as:
Correct
Top Down Estimating
Incorrect
Sorry, that was incorrect.
-
Question 40 of 200
40. Question
You are the project manager of a software company which is involved with creating an anti-virus software product. You are in the execution phase of the project when you realize that there was an omission in defining the scope of the project. What should you do?
Correct
Issue a Change Request
Incorrect
Sorry, that was incorrect.
-
Question 41 of 200
41. Question
In your project, you are presently involved with collecting project records; ensuring that they reflect final specifications; analyzing project success, effectiveness, and lessons learned; and archiving such information for future use. This is done as part of :
Correct
Close Project or phase
Incorrect
Sorry, that was incorrect.
-
Question 42 of 200
42. Question
Risk Acceptance is a strategy that indicates that the project team has decided not to change the project plan to deal with a risk or is unable to identify any other suitable response strategy. The most usual risk acceptance response is to :
Correct
Establish a contingency reserve
Incorrect
Sorry, that was incorrect.
-
Question 43 of 200
43. Question
As a project manager, you must coordinate and direct the various technical and organizational interfaces that exist in the project. For this, it will be beneficial if you have asan input:
Correct
Project Management Plan
Incorrect
Sorry, that was incorrect.
-
Question 44 of 200
44. Question
In a Balanced Matrix Organization,
Correct
Project Manager reports to Functional Manager
Incorrect
Sorry, that was incorrect.
-
Question 45 of 200
45. Question
A car manufacturing company conceptualized a new car which would be more fuel efficient, better ergonomically designed, and satisfies the latest safety compliance. This car was recently launched and has now moved into full fledged production. This is an example of:.
Correct
Project, as this car was conceptualized, designed and now launched. This is a typical scenario where project is intersecting with operation during product lifecycle, notice the word launched. All the activities before launch of the vehicle are part of a project which is temporary activity with a well defined unique output. Once the car moves to production line, it becomes an ongoing operation for the company. Refer PMBOK 5th edition Introduction PN 3.
Incorrect
Sorry, that was incorrect.
-
Question 46 of 200
46. Question
Which of the following statements describes the relationship between project phases and the project life cycle?.
Correct
Collectively, the project phases are known as the project life cycle
Incorrect
Sorry, that was incorrect.
-
Question 47 of 200
47. Question
A project is delivered as per the contract by the project team however the customer is not happy. The customer feels that the deliverable is far below his expectation in terms of quality and functionality and has some serious defects. What should the project manager do in this situation?.
Correct
Proceed to project closure activity. Since the project is delivered as per the contract, the project manager has already fulfilled his obligation and he can move to project closure activity. A contract is a legal document and once signed it represents a mutually binding agreement that obligates the seller to provide a specified product and the buyer to provide monetary compensation. In this case, the deliverable was as per the contract and there is no objective evidence to believe otherwise.
Incorrect
Sorry, that was incorrect.
-
Question 48 of 200
48. Question
Your project has the following information based on Earned Value Analysis, its Earned Value (EV) is $1000, Actual Cost(AC) is $ 850 and Planned Value(PV) is $1050. Which of the following is TRUE about your project ?
Correct
Your project is under budget and behind schedule. Cost Variance = EV-AC = $1000-$850 =$ 150 is positive and Schedule Variance = EV-PV = $1000 – $1050 =-$50 is negative. The project is under budget and behind schedule.)L2) Your project is under budget and behind schedule. Cost Variance = EV-AC = $1000-$850 =$ 150 is positive and Schedule Variance = EV-PV = $1000 – $1050 =-$50 is negative. The project is under budget and behind schedule.
Incorrect
Sorry, that was incorrect.
-
Question 49 of 200
49. Question
Which of the following is NOT an input of the close project or phase process?
Correct
Project management methodology. Correct answer is B. The project management methodology describes the process (or lifecycle) that you use to manage your project.
Incorrect
Sorry, that was incorrect.
-
Question 50 of 200
50. Question
Ashley orders batteries for her project from a new supplier who appears to offer the lowest cost. After delivery of the batteries, the sales representative calls Ashley to thank her for the order. She also sends her an expensive laptop as a thank you gift for her order. What should Ashley do?
Correct
Refuse the gift to avoid the appearance of impropriety. Correct Answer is B. As per PMI’s ethical standards, Ashley should refuse to accept the gift to avoid a case of impropriety.
Incorrect
Sorry, that was incorrect.
-
Question 51 of 200
51. Question
A project manager is employed by a construction company and is responsible for furnishing the completed building. One of the first things that the project manager should do is:
Correct
Create the project charter. As a project manager assigned to the project, he should ensure that the project charter is created and gets authorized by the sponsor. This will assign the project manager to the project and define the high level scope, risks, constraints, and assumptions of the project.
Incorrect
Sorry, that was incorrect.
-
Question 52 of 200
52. Question
You have just been informed by the project sponsor that the customer intends to terminate the project in the middle of the execution process group. Which of the following will you do FIRST as a project manager?
Correct
Evaluate the impact of project closure. Correct Answer is ‘B’. As a project manager, the FIRST thing that the you should do is evaluate the impact of the termination on the stakeholders, organization, subcontractors, and project activities. This will enable you to define a course of action to perform.
Incorrect
Sorry, that was incorrect.
-
Question 53 of 200
53. Question
You have to hire many new team members for a new project. You create an RFP and request HR staffing companies to respond to it, so that you can select the right HR partner for your project. Your wife also runs an HR staffing organization and wants to respond to this RFP. What should you do?
Correct
Update your selection board about your wife also being one of the bidders and request them to treat her proposal objectively like any other proposal. This is a common occurrence in real life. In such cases, the best option is to let the selection committee know that your wife is also a bidder. If the selection committee has any objections, they can reject the bid out right, but if she runs a reputed staffing company, why not let her submit her bid?
Incorrect
Sorry, that was incorrect.
-
Question 54 of 200
54. Question
A customer has been consistently late with approvals on design documentation. The project manager has raised the subject in the past, but the practice of delayed approval has not changed. The project manager has been documenting the delays. Which conflict resolution technique has the project manager been following?
Correct
Withdrawal. Correct Answer is B. Documenting the delay’s is not an attempt to solve the problem. This demonstrates avoidance or withdrawal as the project manager’s response to the situation. Confronting involves attempting to solve the problem for deriving an extent of satisfaction to the parties involved in the issue. The situation described here does not indicate any such attempt.
Incorrect
Sorry, that was incorrect.
-
Question 55 of 200
55. Question
Which of the following is a tool and technique used in ‘Control Communications’ process?
Correct
Meetings. Meetings is a tool and technique used in this process.
Incorrect
Sorry, that was incorrect.
-
Question 56 of 200
56. Question
Which of the following is a disadvantage of a projectized organization?
Correct
No home after project completion. The other three options are advantages of a projectized organization. Since projectized organizations are organized by project, they are efficient in terms of project organization. Also, there is loyalty to the project and communication across project is good. In a functional organization, team members work on project in addition to their regular functional work and they get confused on what to do.
Incorrect
Sorry, that was incorrect.
-
Question 57 of 200
57. Question
Which of the following is NOT a tool and technique used for Acquire Project Team process?
Correct
The tools and techniques for the Acquire project team can be found on Page 267 of PMBOK V5
Incorrect
Sorry, that was incorrect.
-
Question 58 of 200
58. Question
What is the formula for ROI?
Correct
(Gain from investment – cost of investment) / cost of investment. This a dummy question. You can see such questions in the PMI exam whose terminology is known or similar to PMBOK, but are included in the PMI exam to judge the difficulty level
Incorrect
Sorry, that was incorrect.
-
Question 59 of 200
59. Question
During which project management process group is a rough order of magnitude estimate created?
Correct
Initiating. A rough order of magnitude estimate means a very high level estimate. This is generally done during the project initiation phase when very limited information is available about the project.
Incorrect
Sorry, that was incorrect.
-
Question 60 of 200
60. Question
While responding to a procurement request, the seller outlined the detailed technical solution, provided a handful of past customer references and also made a detailed commercial offer. Which procurement document would the seller is most likely going to respond to?
Correct
A RFP requests for a detailed proposal.
Incorrect
Sorry, that was incorrect.
-
Question 61 of 200
61. Question
The popular iterative four step approach of Plan-Do-Check-Act was advocated by which of the following quality theorists ?
Correct
W. Edwards Deming. PDCA (plan-do-check-act) is an iterative four-step problem solving process typically used in business process improvement. It is also known as the Deming cycle, Shewhart cycle, Deming wheel, or plan-do-study-act. It was proposed by W. Edwards Deming in the 1950’s and suggests that business processes should be analyzed and measured to identify sources of variations that cause products to deviate from customer requirements. He recommended that business processes be placed in a continuous feedback loop so that managers can identify and change the parts of the process that need improvements. Plan: Design or revise business process components to improve results. Do: Implement the plan and measure its performance. Check: Assess the measurements and report the results to decision makers. Act: Decide on changes needed to improve the process
Incorrect
Sorry, that was incorrect.
-
Question 62 of 200
62. Question
Project performance reviews using earned value management would typically incorporate information from all the following EXCEPT?
Correct
Cost Benefit Analysis. Cost benefit analysis is a technique that compares positive factors or benefits with negative ones to determine the net result of doing the action. It is a popular technique for the project selection method, but will not be useful during the project performance review. Please refer to PMBOK 5th edition Project Cost Management PN 193 for more details
Incorrect
Sorry, that was incorrect.
-
Question 63 of 200
63. Question
You are a finance specialist who has been assigned to an organization wide project in a Strong matrix structure. The project manager requests you to work on a report, which you do not feel is necessary. You have tried to reason with the project manager about this but the project manager insists it is required. What should you do?
Correct
As a team member, you need to respond to the request – even if you do not personally agree with it. Since you have already tried to reason with the project manager, option-C is also not appropriate
Incorrect
Sorry, that was incorrect.
-
Question 64 of 200
64. Question
In order to determine the target fuel efficiency for a hybrid car being designed, a project manager is looking at published statistics for similar models in the industry. The technique being used is called:
Correct
What the project manager is trying to do is essentially look at the industry benchmark and make sure that the product is in line with it. This is the benchmarking technique
Incorrect
Sorry, that was incorrect.
-
Question 65 of 200
65. Question
As a project manager, you are in the process of establishing the total scope of the effort in the project to define project objectives. For this purpose, you include relevant stakeholders and explore all the aspects of scope, cost, time, risk quality, etc. Which process group of the project are you currently in?
Correct
Planning. The planning process group consists of processes performed to establish the total scope of the effort, define the objectives, and develop the course of action required to attain those objectives. For this purpose, a project manager should include relevant stakeholders and explore all the aspects of scope, cost, time, risk, quality, etc. The result of this planning process group is the project management plan.
Incorrect
Sorry, that was incorrect.
-
Question 66 of 200
66. Question
You are managing one of the most technically challenging and complex projects for your company. In the beginning of the project, there used to be heated arguments on the team regarding the best approach to solving a problem. However, the project is well into the execution stage and the team has finished designing the architecture of the product. They seem to have developed a good understanding of the system. What is the most appropriate way to handle project conflicts at this stage?
Correct
You should let the team explore the best alternatives amongst themselves while you facilitate and support them. A project manager needs to provide more direction in the beginning of the project because he knows the best way to plan the project. However, as the project team matures and develops an understanding during project execution phase, the project manager needs to transition to a support role. Your leadership style could be coaching, facilitating, or supporting.
Incorrect
Sorry, that was incorrect.
-
Question 67 of 200
67. Question
As a project manager you decide to create an issue log which captures issue description, owner, and the target date for issue closure . All of the following are common examples of issues in the project EXCEPT?
Correct
Probable delay in the next delivery. Probable delay in the next delivery represents a project risk and is not an issue as the event is uncertain. This may or may not happen in future.
Incorrect
Sorry, that was incorrect.
-
Question 68 of 200
68. Question
Which of the following is a key output of the Validate Scope process?
Correct
The output of the Validate Scope process is customer acceptance of project deliverables. The other choices all happen during project planning, well before the time the Validate Scope process takes place.
Incorrect
Sorry, that was incorrect.
-
Question 69 of 200
69. Question
A new project manager has asked you for advice on creating a work breakdown structure. After you explain the process to her, she asks you what software she should use to create the WBS and what she should do with it when it is completed. You might respond that it is not the picture that is the most valuable result of creating a WBS. The most valuable result of A WBS is:
Correct
The WBS is an input to all of these choices. However, team buy-in is a direct result of the WBS creation process, while the other choices use the WBS to assist in their completion. Involving the team in creating the WBS provides project team members with an understanding of where their pieces fit into the overall project management plan and gives them an indication of the impact of their work on the project as a whole.
Incorrect
Sorry, that was incorrect.
-
Question 70 of 200
70. Question
All of the following are outputs of the Estimate Costs process Except:
Correct
This question is asking, “When you finish estimating costs, what do you have?” Many people who do not realize that estimates should be in a range pick that option. Documentation of assumptions is referring to the basis of estimates, which is an output of Estimate Costs. The prevention of inappropriate changes is more correctly part of the cost management plan and the change control system.
Incorrect
Sorry, that was incorrect.
-
Question 71 of 200
71. Question
If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that this risk event will occur during the fourth month of the project?
Correct
No calculation is needed. If there is a 20 percent chance in any one month, the chance in the fourth month must therefore be 20 percent.
Incorrect
Sorry, that was incorrect.
-
Question 72 of 200
72. Question
The primary objective of contract negotiations is to:
Correct
As a project manager, you want to develop a good relationship during negotiations that will last throughout the project. Negotiations are not about getting the most from the other side (win-lose), as such actions will not create a good relationship. That doesn’t mean the buyer sacrifices doing what is best for the organization.
Incorrect
Sorry, that was incorrect.
-
Question 73 of 200
73. Question
Your project has been fast tracked and you are looking to quickly bring in a subcontractor to complete networking. There is no time to issue a request for proposal (RFP), so you choose to use a company you have used many times before for software development. A primary concern in this situation is :
Correct
Although you have used this contractor before, how can you be sure the company is qualified to do the new work, since it is not exactly like the previous work? This is the risk you are taking.
Incorrect
Sorry, that was incorrect.
-
Question 74 of 200
74. Question
Rekha is a project manager on a large construction project. Late in the project, her client demands a big change. She assesses the impact of the change and tells the client how much time and money it will cost. But the client says that he doesn’t have the time or budget to allow the change. What’s the best way for rekha to handle this situation?
Correct
Hold a meeting with the client to figure out why he’s asking for the change
Incorrect
Sorry, that was incorrect.
-
Question 75 of 200
75. Question
The project manager for a construction project discovers that the local city council will vote on a zoning change that would open up a new neighborhood to commercial building. She contacts other construction companies in the area that would benefit from eh change to ask them to attend the council meeting in order to convince the city council to vote for the change. A “Yes” vote will benefit all of the companies. This is an example of which risk response strategy?
Correct
Share
Incorrect
Sorry, that was incorrect.
-
Question 76 of 200
76. Question
Which of the following is the BEST example of a reward system?
Correct
Everyone will get a bonus of $500 if the project meets its quality goals, $500 if it meets its budget goals, and $600 if it comes in on time.
Incorrect
Sorry, that was incorrect.
-
Question 77 of 200
77. Question
Amit is the manager of a software project. His client has agreed on project Scope statement at the beginning of the project, but whenever the client verifies deliverables, he comes up with features that the would like to add into the product. Amit is working with the client to find what requirements were missed in the planning stages of the project and how to plan better in the future. What is the BEST description of his project’s current situation?
Correct
Scope creep
Incorrect
Sorry, that was incorrect.
-
Question 78 of 200
78. Question
As you determine the requirements, constrains and assumptions for the project you record them in which documents?
Correct
Project scope statement
Incorrect
Sorry, that was incorrect.
-
Question 79 of 200
79. Question
Your project just completed, and one of your subcontractors has sent you floor seats to the next big hockey game to thank you for your business. What is the BEST way to respond?
Correct
Thank the subcontractor, but politely refuse the gift
Incorrect
Sorry, that was incorrect.
-
Question 80 of 200
80. Question
You are in process of defining how to plan and execute the risk managementactivities for your project. Which of the following statements are false?
Correct
The inputs to this process includes the project scope statement, project management plan, and the risk register
Incorrect
Sorry, that was incorrect.
-
Question 81 of 200
81. Question
Which of the following establishes the procedures to transfer the project product or services to production and / or operations?
Correct
Administrative closure procedure
Incorrect
Sorry, that was incorrect.
-
Question 82 of 200
82. Question
Weighting systems, screening systems, and independent estimates are tools of which process?
Correct
Conduct procurement
Incorrect
Sorry, that was incorrect.
-
Question 83 of 200
83. Question
Your project team is already created the WBS, developed estimates for the work packages, and sequenced the project activities using the precedence diagramming method. Which action should be performed NEXT?
Correct
Apply schedule compression techniques
Incorrect
Sorry, that was incorrect.
-
Question 84 of 200
84. Question
Benchmarking is a common tool used for:
Correct
Plan Quality
Incorrect
Sorry, that was incorrect.
-
Question 85 of 200
85. Question
Work Breakdown Structure is:
Correct
A deliverable oriented grouping of project components
Incorrect
Sorry, that was incorrect.
-
Question 86 of 200
86. Question
All the following are advantages of GERT (Graphical Evaluation and Review Techniques) as compared with PERT (Project Evaluation and Review Technique)except:
Correct
Allows for dummy tasks
Incorrect
Sorry, that was incorrect.
-
Question 87 of 200
87. Question
Quantitative assessments of the likely costs of the resources required to complete project activities is also referred to as:
Correct
Cost Estimates
Incorrect
Sorry, that was incorrect.
-
Question 88 of 200
88. Question
Close Project or Phase is used for generating, gathering, and disseminating information to formalize a phase or project completion. All the following are outputs for Close Project or Phase EXCEPT:
Correct
Change Requests
Incorrect
Sorry, that was incorrect.
-
Question 89 of 200
89. Question
Your Management is evaluating a project which requires an investment of $ 500,000. The expected inflow is $ 100,000 for 1st year and $ 300,000 for every year after that. What is the payback period?
Correct
2 years, 4 months
Incorrect
Sorry, that was incorrect.
-
Question 90 of 200
90. Question
Plan Risk Responses helps in developing procedures and techniques to enhance opportunities and reduce threats to the project`s objectives. All the following tools help in Plan Risk Responses EXCEPT:
Correct
Work breakdown structure(WBS)
Incorrect
Sorry, that was incorrect.
-
Question 91 of 200
91. Question
You are the project manager for a software company, and are in the process of developing an approximation of the costs of the resources needed to complete project activities. In approximating the cost, you are considering the causes of variation of the final estimate for purpose of better managing the project. This is done as part of:
Correct
Estimate Costs
Incorrect
Sorry, that was incorrect.
-
Question 92 of 200
92. Question
As a project manager, you understand that risk ratings and prioritization may change during the life of the project. So, you make project risk an agenda at all team meetings andschedule regular:
Correct
Project risk reviews
Incorrect
Sorry, that was incorrect.
-
Question 93 of 200
93. Question
Description of how a project management team should implement the overall intentions and direction of an organization with regards to quality (as expressed by top management) is available in:
Correct
Quality Management Plan
Incorrect
Sorry, that was incorrect.
-
Question 94 of 200
94. Question
All the following statements about Risk Management processes in real-life project situations are correct EXCEPT:
Correct
Processes always have discrete elements with well-defined interfaces
Incorrect
Sorry, that was incorrect.
-
Question 95 of 200
95. Question
Tom always delivers his projects on time and within budget. He believes that his success can be explained by the fact that he makes all of the project decisions himself and then enforces those decisions with an iron hand. What is his management style?.
Correct
McGregor’s Theory X. McGregor’s Theory X asserts that the average person dislikes work inherently and that effective management lies in threats, intimidation and minimal involvement of the individual in work decisions.
Incorrect
Sorry, that was incorrect.
-
Question 96 of 200
96. Question
A project is in the final stages of testing when it receives a major change request from the customer which would delay the final delivery of the project by 2 weeks. What should the project manager do NEXT?
Correct
Communicate the implication of the change to the customer. The next step is to communicate the impact on the final delivery to the customer and get his approval, especially because it affects the final delivery date of the project. Option (a
Incorrect
Sorry, that was incorrect.
-
Question 97 of 200
97. Question
As a project manager, you are assigned to a project that has been outsourced. The next step is to organize a formal bidding process and select the vendor for the project. You own stock in one of the vendor companies who participated in the bidding process. What is the BEST course of action for you?
Correct
Tell your manager and remove yourself from the vendor selection committee.
Incorrect
Sorry, that was incorrect.
-
Question 98 of 200
98. Question
Which of the following is NOT true about a project?.
Correct
It is an ongoing work and it follows organizational procedures. We all love to answer this question! Ongoing repetitive work with no unique output is an operation and not a project. All the other options (a
Incorrect
Sorry, that was incorrect.
-
Question 99 of 200
99. Question
An organization has created a special project team to handle a critical project. The team members of this project are full-time dedicated to the project and are pulled from different functional departments. They also have their own set of operating procedures. This organization structure is MOSTLY?
Correct
Composite. This is an example of a composite form of organizational structure. Some organizations fall somewhere between the fully functional and pure matrix and even a fully functional organization can create a special project team to handle critical project. The team members of this project are full-time dedicated to the project and are pulled from different functional departments. They also have their own set of operating procedures and may operate outside standard reporting structure
Incorrect
Sorry, that was incorrect.
-
Question 100 of 200
100. Question
Voice mail and e-mail are examples of,.
Correct
Push Communication. Letter, memos, faxes, e-mails and voice mails are examples of Push communication
Incorrect
Sorry, that was incorrect.
-
Question 101 of 200
101. Question
A pharmaceutical company recently terminated a research project because it no longer seems commercially viable for the company. What is the FIRST thing the project manager should do?
Correct
Conduct Scope Validation. In the event of project termination, the project manager should do scope validation to determine the extent of completion of the project. In this case, scope validation is measured against the deliverables to the point of the project cancellation. Options (a) and (b) can be done later.)L2) Conduct Scope Validation. In the event of project termination, the project manager should do scope validation to determine the extent of completion of the project. In this case, scope validation is measured against the deliverables to the point of the project cancellation. Options (a) and (b) can be done later.
Incorrect
Sorry, that was incorrect.
-
Question 102 of 200
102. Question
Which of the following is a tool to perform qualitative risk analysis process?.
Correct
Probability-Impact matrix is used in analyzing the probability and impact of the identified risks)L2) Probability-Impact matrix is used in analyzing the probability and impact of the identified risks
Incorrect
Sorry, that was incorrect.
-
Question 103 of 200
103. Question
Earned value implementations can be scaled along the dimensions of granularity and frequency to achieve the degree of rigor required by the significance and the uncertainty of the project. Which of the following truly explains granularity?
Correct
Level of detail to which the project works scope is broken down using a WBS. Correct Answer is ‘C’. Granularity refers to the level of detail to which the project work scope is broken down using a WBS.
Incorrect
Sorry, that was incorrect.
-
Question 104 of 200
104. Question
For the monthly status meeting with the project’s key stakeholders, you have prepared your project report using earned value calculations. Your project shows a CPI < 1 and SPI < 1 and you are worried that the stakeholders may be unhappy with the project performance. One of your friends suggests you alter the data, so you form a near perfect performance curve. What should you do?
Correct
Provide true information about the project performance and explain the reasons. Correct Answer is C. As per the PMI’s professional responsibility guidelines, you should provide accurate and truthful representations in your reports.
Incorrect
Sorry, that was incorrect.
-
Question 105 of 200
105. Question
John has been promoted to a project manager from his technical post and has also been assigned a small sized project. He is very excited about managing and delivering this project. Management has asked Midas, who has more than 15 years of project management expertise, to mentor him. Midas has asked John to create the work breakdown structure. Which of the following could Midas have told John while explaining why the WBS should be used?
Correct
. Correct Answer is C. WBS graphically displays the work to be done on the project and also can be shared with the customer to confirm understanding and to fine tune the project and product scope
Incorrect
Sorry, that was incorrect.
-
Question 106 of 200
106. Question
You are working on a project when the customer calls to explain that he wants another feature added to the product. However, there is no additional budget for the new feature. What should you do?
Correct
Follow the contract change control process. Remember, whenever there is a change, the right process is to follow change control. In this case, the customer is asking for a change, so follow the change control process. It’s quite possible that you can remove the old feature and add the new feature at the same cost, but it should be done following the change control process.
Incorrect
Sorry, that was incorrect.
-
Question 107 of 200
107. Question
You are managing a construction project using a firm fixed price (FFP) contract. The contract is structured so that your company will be paid a fee of $85,000 to complete the work. There was a $15,000 overhead cost that your company had to cover. It’s now three months into the project and your costs have just exceeded $70,000. The project has now consumed the entire fee and your company will now be forced to pay for all costs on the project from this point forward. What’s the BEST way to describe this situation?
Correct
The project has reached the point of total assumption. The point of total assumption is the point at which the seller assumes the costs. In a firm fixed price contract, this is the point where the costs have gotten so large that the seller basically runs out of money from the contract and has to start paying the costs.
Incorrect
Sorry, that was incorrect.
-
Question 108 of 200
108. Question
Which of the following statements describes the relationship between the project phases and the project life cycle?
Correct
Phases are divisions within a project where extra control is needed to effectively manage the completion of a major project deliverable. The high level nature of project phases makes them an element of the project life cycle. For more information, please refer to PMBOK 5th Edition Page No. 41.
Incorrect
Sorry, that was incorrect.
-
Question 109 of 200
109. Question
As a project manager, what would you give the highest priority: quality, cost, or schedule?
Correct
It would depend upon the project. Quality, cost, and schedule are all part of the triple constraints, so they are equally important. Which one to compromise on is project specific.
Incorrect
Sorry, that was incorrect.
-
Question 110 of 200
110. Question
You just started administrating a contract when the senior management of your organization decides to terminate the contract. What should you do?
Correct
Follow the Close Contract Process. A contract is either terminated or it’s completed because the scope of work is completed. In either case, the contract closure process needs to be followed to ensure that you have historical information about the contract.
Incorrect
Sorry, that was incorrect.
-
Question 111 of 200
111. Question
You are sent by your company to execute a project in a foreign country. All of your equipment is detained at the airport and the airport authority asks for a fee to release the equipment. You are also losing time on your project. What would you do?
Correct
Establish whether such payment is legal in that company. Before jumping the gun, establish whether they are asking for a fee or a bribe. If it’s a bribe, don’t pay. If it’s an airport usage fee, please go ahead and pay.
Incorrect
Sorry, that was incorrect.
-
Question 112 of 200
112. Question
You have been assigned as the project manager of a new e-business project. There appear to be many risks on the project, but nobody has evaluated them to assess the range of possible outcomes. What was not done?
Correct
Risk Analysis. This can include qualitative or quantitative risk analysis. I hope this was an easy question for you.
Incorrect
Sorry, that was incorrect.
-
Question 113 of 200
113. Question
Using the Blake Mouton managerial grid which is focused on task versus person where would country club leadership fall?
Correct
High People Low Production. This style of leader is most concerned about the needs and feelings of members of his/her team. These people operate under the assumption that as long as team members are happy and secure then they will work hard. What tends to result is a work environment that is very relaxed and fun, but where production suffers due to lack of direction and control. This a dummy question. You can see such questions in the PMI exam whose terminology is known or similar to PMBOK but are included on the PMI exam to judge the difficulty level
Incorrect
Sorry, that was incorrect.
-
Question 114 of 200
114. Question
Standard deviation is a measure of :
Correct
Standard deviation is the measure of how far the measurement is from the mean. You are not expected to be an expert in statistics to pass the PMP exam, but some knowledge about normal distribution and bell curves is required. You can get the required information in Lesson number 8 of Simplilearn PMP Preparation Course.
Incorrect
Sorry, that was incorrect.
-
Question 115 of 200
115. Question
Which of the following is not used in selecting between multiple competing projects?
Correct
Earned Value Technique. The earned value technique is not a project selection method, but a method to track the project progress. All of the others are project selection methods. In order to find out more project selection methods, please refer to Lesson number 7 of Simplilearn PMP Preparation Course.
Incorrect
Sorry, that was incorrect.
-
Question 116 of 200
116. Question
Which of the following is NOT an example of the cost of quality?
Correct
Assigning two team members to work on the product development. All of the other options come under the cost of quality. If you are not sure of what is cost of quality, please refer to Lesson number 8 of Simplilearn PMP Preparation Course
Incorrect
Sorry, that was incorrect.
-
Question 117 of 200
117. Question
You are the project manager of a new road construction project with a total budget of $500,000. During a status review meeting you realized that your team has just completed 40% of the work when they should have completed 50% by now. They have also spent $190,000 so far on the project. What’s the best way to describe the project status ?
Correct
Project is behind schedule but within the budget. If you look at the details, it says that the project should have been 50% completed, but it’s only 40% complete, i.e. it’s behind schedule. Also, if only 40% of the work is completed, the project should have used only $500,000*0.4= $200,000. Since the question says that only $190,000 has been spent, the project is within budget as well. This problem can be solved using the earned value technique.
Incorrect
Sorry, that was incorrect.
-
Question 118 of 200
118. Question
Which of the following is the correct order of actions that you take during the closing processes?
Correct
Get formal acceptance, write lessons learned, hand over deliverable to stakeholder(s), close the contract. One important fact is that you need your team’s help when you’re writing the lessons learned. That’s why you can’t release the team until the lessons learned are documented and added to the organizational process assets. Also, the last thing you do on the project is close the contract. Remember, release the project team is no longer part of closing as per the new RDS study conducted by PMI.
Incorrect
Sorry, that was incorrect.
-
Question 119 of 200
119. Question
A project manager is planning the project and he is creating a plan to describe how human resource requirements in the project would be met. He is using a bar chart tool called a resource histogram for charting this requirement. However, he notices that some of the individual bars in the resource histogram extend beyond the maximum allowed hours. What should the project manager do to correct it?
Correct
Resource Leveling. Resource leveling is required whenever individual bars in the resource histogram extend beyond the maximum allowed hours. Resource leveling can be done by either adding more resources or modifying the schedule. Option (a) Reducing scope or (b) extending working hours would be detrimental to the project’s success and is not recommended here. Option (d) schedule compression which can be done through either crashing or fast tracking wouldn’t necessarily be helpful. Since specific bars are showing an overflow, it can be best tackled using resource leveling.
Incorrect
Sorry, that was incorrect.
-
Question 120 of 200
120. Question
A hospital is installing a new management system to computerize the hospital functions. For this purpose, representatives from several departments are selected to create a task force assigned to implement the project. This organization structure is called?
Correct
Composite Organization. Many times even a fundamentally functional organization may create a special project team to handle a critical project. This may have many characteristics of a project team in a projectized organization. The team may include full-time staff from different functional departments, may develop its own set of operating procedures, and may operate outside the standard, formalized reporting structure.
Incorrect
Sorry, that was incorrect.
-
Question 121 of 200
121. Question
During Which process group does the team measure and analyze the work being done on the project?
Correct
During monitoring and controlling, project performance is measured and needed changes are identified and approved.
Incorrect
Sorry, that was incorrect.
-
Question 122 of 200
122. Question
If project time and cost are not as important as the number of resources used each month, which of the following is the best thing to do?
Correct
Fast tracking affects both time and cost but may not help even out resource usage. Monte Carlo analysis and analysis of life cycle costs do not directly deal with resources. Resource optimization is the only choice that will definitely affect resources.
Incorrect
Sorry, that was incorrect.
-
Question 123 of 200
123. Question
You have a project with the following activities: Activity A takes 40 hours an can start after the project starts. Activity B takes 25 hours and should happen after the project starts. Activity C must happen after activity A and takes 35 hours. Activity D must happen after activities B and C and takes 30 hours. Activity E must take place after activity C and takes 10 hours. Activity F takes place after activity E and take 22 hours. Activities F and D are the last activities of the project. Which of the following is TRUE if activity B actually takes 37 hours?
Correct
Did you notice how difficult this question was to read? Such wording is intentional, to prepare you for interpreting questions on the real exam. Looking at this situation, you see there are three paths through the network as shown in the following table. If the duration of activity B changes from 25 to 37, the activity will take 12 hours longer. As the activity is only on the third path, it will only change the duration of that path from 55 to 55 + 12, or 67 hours. Since the duration of the critical path is 107 hours, the delay with activity B will have no impact on the project timeline or the current critical path. Start, A, C, E, F, End=107, Start, A, C, D, End=105, Start, B, D, End =55
Incorrect
Sorry, that was incorrect.
-
Question 124 of 200
124. Question
You provide a provide cost estimate for the project to the project sponsor. He is unhappy with the estimate, because he thinks he price should be lower. He asks you to cut 15 percent off the project estimate. What should you do?
Correct
This question is full of choices that are not correct project management actions. To answer the question, you must first realize that it is never appropriate for a project manager to just cut estimates across the board. You should have created a project estimate based on realistic work package estimates that do not include padding. Then, if costs must be decreased, you can look to cut quality, decrease risk, cut scope, or use cheaper resources (and at the same time closely monitor the impact of changes on the project schedule). One of the worst things a project manager can do is to start a project knowing that the time or cost for the project is unrealistic. Did you notice the choice of adding additional resources? Even though they have low hourly rates, that would add cost. Evaluating, looking for alternatives, and then reporting the impact of the cost cutting to the sponsor is the best action to take.
Incorrect
Sorry, that was incorrect.
-
Question 125 of 200
125. Question
The project team has created a plan for how they will implement the quality policy. It addresses the organization structure, responsibilities, procedure, and other information about plans for quality. If this plan changes during the project. Which of the following plans will also change?
Correct
The plan described is the quality management plan. Since the quality management plan is included in the project management plan, changing the quality management plan will also change the project management plan.
Incorrect
Sorry, that was incorrect.
-
Question 126 of 200
126. Question
As the project manager, you are preparing your quality management plan. You are looking for a tool that can demonstrate the relationship between events and their resulting effects. You want to use this tool to depict the events that cause a negative effect on quality. Which of the following is the best choice for accomplishing you objective?
Correct
All reports and diagrams are communications tools. This question asks you to pick the most appropriate quality tool to help communications. An Ishikawa diagram, also called a cause and effect diagram, is more appropriate than a Pareto diagram since you are trying to determine the causes. Once causes are known and you have data on occurrences, the data can he displayed in a Pareto diagram.
Incorrect
Sorry, that was incorrect.
-
Question 127 of 200
127. Question
During the first half of the project, five members left for other projects without being replace, two team members went to vacation without informing you, and other team members expressed uncertainty about the work they were to complete. In this situation, it is best if you create a ________ for the second half of the project.
Correct
The resource histogram shows the resources used per time period, but would provide limited benefit in this situation. The responsibility assignment matrix cross-references resources with the activities or work packages they are to accomplish, but it does not show when they will be required to do their work. The staffing management plan describes when resources will be brought onto and taken off the project, and would provide the most benefit for this project.
Incorrect
Sorry, that was incorrect.
-
Question 128 of 200
128. Question
You were in the middle of a two-year project to deploy new technology to field offices across the country. A hurricane caused power outages just when the upgrade was near completion. When the power was restored, all of the project reports and historical data were lost with no way to retrieving them. What should have been done to prevent this problem?
Correct
The risk is the loss of data due to a power outage. Purchasing insurance is not related to preventing the problem. It transfers the risk. Creating a reserve fund is acceptance of the risk, and would help address the cost factors after the power failure, but would not reduce the probability or impact of it. Avoiding the hurricane by scheduling the installation at a different time reduces the power outage risk, but could have a large negative impact on the project schedule and so is not the best choice. The better choice of the options is to monitor the weather and know when to implement the contingency plan.
Incorrect
Sorry, that was incorrect.
-
Question 129 of 200
129. Question
A project manager on a multinational website implementation project is at a party and talks to friends who will be heavy users of this new website when the project is complete and the site is rolled out. They describe some annoying aspects of the current website. The project manager takes best describes what the project manager has done?
Correct
Scope validation is a control function related to gaining customer acceptance. Integrated change control relates to looking for multiple impacts of changes. Scope planning creates a scope management plan. The project manager has performed stakeholder analysis by learning stakeholder requirements, and making recommendations to fulfill those requirements.
Incorrect
Sorry, that was incorrect.
-
Question 130 of 200
130. Question
Which of the following shows roles and responsibilities on your project?
Correct
RACI matrix
Incorrect
Sorry, that was incorrect.
-
Question 131 of 200
131. Question
While identifying risks for a new construction project, you discover that a chemical you are using on your building cannot be applied in rainy conditions. You also learnt that you project will be ready for the chemical application around the time when most of the rainfall happens in this part of the country. Since the project can’t be delayed until after the rainy season and you need to make sure the building gets the chemical coating, you decide that your team will just have to work around the rain. This is an example of which strategy?
Correct
Accept
Incorrect
Sorry, that was incorrect.
-
Question 132 of 200
132. Question
A change has occurred on your project. You’ve documented the change, filled out a change request, and submitted that request to the change control board (CCB). What’s the NEXT thing that must happen on the project?
Correct
Stakeholders on the CCB use expert judgment to evaluate the requested change for approval.
Incorrect
Sorry, that was incorrect.
-
Question 133 of 200
133. Question
You are the project manager on a construction project. As you’re planning out the work your team will do, you divide up all of the work into work packages and create a WBS that shows how they fit into categories. For each one of the work packages, you write down details such as initial estimates and information about what account it should be billed against. Where do you store all of that information?
Correct
WBS Dictionary
Incorrect
Sorry, that was incorrect.
-
Question 134 of 200
134. Question
Which of the following is NOT found in a project charter?
Correct
Procedures for managing changes to contracts
Incorrect
Sorry, that was incorrect.
-
Question 135 of 200
135. Question
Your are managing a project where you work with 7 other team members and two sponsors. How many lines of communications are there between stakeholders on this project?
Correct
45
Incorrect
Sorry, that was incorrect.
-
Question 136 of 200
136. Question
Which of the following is not an output of closing project?
Correct
Contract document
Incorrect
Sorry, that was incorrect.
-
Question 137 of 200
137. Question
Project Success is measured by:-
Correct
Product and project quality, timeliness, budget, compliance, and degree of customer satisfaction
Incorrect
Sorry, that was incorrect.
-
Question 138 of 200
138. Question
You are the project manager assigned to install the electrical wiring for a 20,000square foot office building that is currently under construction. You are trying toestimate the costs of this project. You know from past experience that is costsapproximately $3 per square foot to properly wire and entire building. As your buildingwill be 20,000 square feet you estimate that the project will cost approximately$60,000. What type of estimating technique did you use?
Correct
Parametric estimating
Incorrect
Sorry, that was incorrect.
-
Question 139 of 200
139. Question
Earned value analysis is a report performance tool/ technique used in manage stakeholder’s process. Which of the following performance measurements is derived by the following formula: (EAC-AC) ?
Correct
ETC
Incorrect
Sorry, that was incorrect.
-
Question 140 of 200
140. Question
A manager works very closely with his subordinates to create an effective working environment. Once a new person is hired, he works with the employee to set realistic goals for the short term and longterm. In addition he continuously works with employee to discuss career path and career ambitions. He is constantly coaching, counseling and meeting. Once his employees reach the goal, he reward them with merit, increases/bonus , offer expanded job responsibilities, with new Challenges, which of the following motivational theories are least utilized in his management approach to motivating his employees?
Correct
Self-efficacy theory
Incorrect
Sorry, that was incorrect.
-
Question 141 of 200
141. Question
You are in the process of identifying and documenting the logical relationships among schedule activities. Which of the following are NOT outputs from this process?
Correct
. Milestones list
Incorrect
Sorry, that was incorrect.
-
Question 142 of 200
142. Question
Which of the following are not Project Management Knowledge Areas?
Correct
Project Configuration Management
Incorrect
Sorry, that was incorrect.
-
Question 143 of 200
143. Question
Risk identification helps in determining which risks might affect the project and documenting their characteristics. All the following are tools and techniques to Identify Risks EXCEPT:
Correct
Risk Probability and Impact
Incorrect
Sorry, that was incorrect.
-
Question 144 of 200
144. Question
. In your project, you are using Project files, commercial cost-estimating databases and project team knowledge to determine the cost of many categories of resources. This will help you in determining estimate of the costs of the resources needed to complete project activities. This information is available to you as part of :
Correct
historical information
Incorrect
Sorry, that was incorrect.
-
Question 145 of 200
145. Question
As a project manager, you realize the importance of developing project team for Project human resource management. Develop Project Team helps in developing individual and group competencies to enhance project performance. All the following are inputs toDevelop Project Team EXCEPT:
Correct
Project interfaces
Practice of PMP questions can make your exam preparation complete, in our three step study plan we give good importance to practice step
Here are the 200 questions which can strengthen your preparation and can help in identification of weak areas.
Take the free practice test and find out how ready you are for PMP Examination with strong understanding of PMBOK knowledge areas and process groups.
Good Luck